years. In its February 5 order, the SCC stated: Under the VCEA, Dominion must engage in robust planning to achieve the policy goals therein in a cost-effective manner. 1193 and ch. Dominion’s process in Virginia is not expected to wrap up until 2021, so the current pandemic may not directly impact the process, NRDC’s Levin said. On May 8, 2020, the Company filed a letter informing the Commission that Dominion intended to supplement its 2020 IRP filing on or before May 15, 2020. The Commission will meet on February 12 at 10 am and provide an opportunity for public testimony on the issues raised by the February 5 order (PUR-2020-00134 ). Community   |    Instead of charting the electric utility’s pathway to zero carbon emissions, it announced its intent to hang on to all its gas plants, and even add to the number. The company is projecting that residential rates will keep pace with historic levels of annual inflation, with a compound annual growth rate of around 3% over the next 10 years. You are now leaving Dominionenergy.com. Plan_public version. accepted the REPS compliance plans filed by DEP, DEC, and Dominion as a part of the Commission’s review of each utility’s integrated resource planning (IRP) update reports. DEC's Integrated Resource Plan, 2020 REPS Comp. These investments will ensure continued grid stability, needed capacity, and improved resiliency, and will enable additional renewable resources to come online. For additional insights, click. What is an integrated resource plan (IRP)? The rate is also the lowest of all states participating in the Regional Greenhouse Gas Initiative, which Virginia will join under the Virginia Clean Economy Act and companion legislation. Provided below are the associated materials from the two IRP Forums and one pre-filing Webinar that Duke Energy held with North Carolina and South Carolina stakeholders in 2020. DESC 2020 IRP The more things change, the more they stay the same. Dominion Energy Virginia filed its 2020 Integrated Resource Plan on May 1. Dominion Energy Virginia filed its 2020 Integrated Resource Plan on May 1. Also included in this year's filing is a significant increase in energy efficiency programs to meet the 5% energy sales reduction target by 2025 set by the VCEA. Dominion “is continuing to evaluate the logistics for filing the 2020 [IRP] in light of the ongoing public health emergency,” the utility wrote in … December 23, 2020: On December 23, the South Carolina Public Service Commission (PSC) fully rejected Dominion Energy South Carolina's (DESC) 2020 Integrated Resource Plan (IRP) and required DESC to file a Modified 2020 IRP within 60 days. News from Dominion Energy. About Us, Careers   The increase is driven, in part, by Governor Ralph Northam's executive order on climate change and the Virginia Clean Economy Act passed by the General Assembly. Dominion Energy’s proposed integrated resource plan, filed with the Virginia State Corporation Commission (SCC) on May 1, 2020, has been rejected as insufficient. RICHMOND, Va., May 1, 2020 /PRNewswire/ -- In just one year, Dominion Energy Virginia has quadrupled the amount of solar and wind generation in its 15-year, long-term integrated resource plan (IRP). Earlier this week, Duke Energy Carolinas (DEC) and Duke Energy Progress (DEP) filed their 2020 Integrated Resource Plans (IRP) with the North Carolina Utilities Commission (NCUC). |    Winter peak load forecasted annual growth fell from 0.9% in DESC’s 2019 IRP to 0.7% in the 2020 IRP. Ralph Northam signed the act into law. The IRP is a 15-year plan projecting future energy demand, costs, and how Dominion proposes to meet customer’s energy needs and the Commonwealth’s clean energy requirements. Also since the Commission’s 2019 report, the Commission has issued orders approving REPS compliance reports and accepting REPS Dominion may actually have conceded as much in its re-filed IRP. On May 1, 2020, Dominion filed its 2020 IRP with the Commission. Files: 9/1/2020: Filing: Dominion Energy North Carolina Statement of Capacity Need. RICHMOND, Va., May 1, 2020 / PRNewswire / -- In just one year, Dominion Energy Virginia has quadrupled the amount of solar and wind generation in its 15-year, long-term integrated resource plan … Dominion Energy Virginia's residential rates are 11.62 cents per kilowatt-hour — nearly 10 percent below the national average of 12.85, according to the U.S. Energy Information Administration. Projected expansion of offshore wind, solar, and energy storage development amounts to approximately 24,000 new megawatts of renewable energy and storage capacity over the next 15 years. Virginia law now requires the company to submit an IRP every three years. This is the largest solicitation in the Company's history for renewable energy in a calendar year and will promote its efforts toward a clean energy future. Investors   The company is committed to sustainable, reliable, affordable and safe energy and is one of the nation's largest producers and transporters of energy with more than $100 billion of assets providing electric generation, transmission and distribution, as well as natural gas storage, transmission, distribution and import/export services. The company is committed to achieving net zero carbon dioxide and methane emissions from its power generation and gas infrastructure operations by 2050. Suppliers. Dominion Energy recently announced a new companywide goal of achieving net zero emissions, covering both carbon dioxide and methane in its power generation and natural gas operations across 20 states by 2050. This includes battery storage pilots already approved and scheduled to be online in. In its February 5 order, the SCC stated: As a reminder, the Duke Energy (Duke) and Dominion utilities in North Carolina are required to submit new IRPs to the NCUC for approval. As Dominion’s Economic Resource Commitment Manager Eric Bell noted, that would imply that the IRP “is the driving document behind actually executing the plans that are proposed.” Dominion’s proposed IRP, he later testified, “actually doesn’t propose any … By clicking OK you will be redirected to an external site. More than 7 million customers in 20 states energize their homes and businesses with electricity or natural gas from Dominion Energy (NYSE: D), headquartered in Richmond, Va. Dominion Energy's solar fleet, already the 4, Energy storage capacity is projected to expand to approximately 2,700 megawatts, meeting the most ambitious targets in the country set in the VCEA. BRA clearing prices for Delivery Years 2019-2020 through 2022022, (2) 1-converted to a cents/kWh onpeak capacity purchase price, (3) applied to the - years of the Schedule 19LMP contract that correspond to the Company’s - capacity need as identified in its IRP, and (4) levelized over the course of 2018 the ten-year contract. Dominion is required to update its planning assumptions relating to the energy and demand forecast, commodity fuel price inputs, renewable energy forecast, energy efficiency and demand-side management forecasts, and changes to projected retirement dates of existing units in its Modified 2020 IRP and in future IRPs. Donate Today! The DESC IRP is rejected and must be modified to meet more detailed best management Safety   |    The Commission, however, cannot conclude, based on the record in this proceeding and issues discussed further below, that Dominion’s 2020 IRP, as filed, is reasonable and in the public interest for purposes of a planning document. Advocates pushed back and the response from the Commission was unambiguous – it rejected Dominion’s IRP in late 2020 and required the company to perform a “rapid assessment” and include annual efficiency savings of at least 1%. The plan was to have included information related to the Virginia Clean Economy Act (VCEA) enacted by the General Assembly in 2020. The increase is driven, in part, by Governor Ralph Northam's executive order on climate change and the Virginia Clean Economy Act (VCEA) passed by the General Assembly. For questions regarding documents not linked call 801-530-6716 Files: 9/1/2020: Filing: DEC and DEP Notice Rescheduling Second ISOP Stakeholder Forum. More than 5,000 megawatts of offshore wind is planned by 2035, including the 2,600 MW Coastal Virginia Offshore Wind project already announced by Dominion Energy. Dominion Energy Virginia has quadrupled the amount of solar and wind generation in its 15-year, long-term integrated resource plan (IRP). But it paints a gloomy picture for its customers. "We are putting Virginians to work on renewable energy projects that will create thousands of jobs, transforming the environment and the economy of the Commonwealth.". Files: 9/1/2020: Filing: Confidential Pages from DEC 2020 IRP. Many factors were considered in the load forecast including historical sales data, economic factors impacting the Company’s commercial and residential customers, DSM which includes energy efficiency (“EE”) and load management, and EVs. Customers and developers interested in learning more about Dominion Energy's renewable energy expansion plans may contact us via email: 2020SolarWindRFP@dominionenergy.com. Dominion Energy’s proposed integrated resource plan, filed with the Virginia State Corporation Commission (SCC) on May 1, 2020, has been rejected as insufficient. For its 2023 IRP cycle, Dominion must go even further, analyzing annual efficiency savings all the way up to 2%. The new schedule begins with Dominion’s next plan to be filed in May of 2020. Dominion’s solar fleet is projected to grow due to the IRP, which calls for the development and procurement of 16,000 MW in the state over the next 15 years. News   The company is making essential upgrades to the transmission infrastructure in Virginia and is embarking on strategic investments on the distribution system through its Grid Transformation Plan. For questions regarding documents not linked call 801-530-6716 |    The 2020 Integrated Resource Plan presented by Dominion would make an excellent presentation for financial analysts and investors. Please visit DominionEnergy.com to learn more. Bidders seeking more information on the competitive bidding process and the RFP submittal documents should visit: www.dominionenergy.com/2020SolarWindRFP. Since the Commission’s 2018 report, the Commission has also issued orders approving REPS compliance reports and accepting REPS Dominion Energy Virginia filed the 2020 IRP on May 1, little more than two weeks after Gov. Instead of charting the electric utility’s pathway to zero carbon emissions, it announced its intent to hang on to all its gas plants, and even add to the number. In brief, we find significant deficiencies in the 2020 Integrated Resource Plan of Dominion Energy South Carolina, Inc. ("Proposed IRP") filed by DESC with this Commission on February 28, 2020-and supplemented on August 28, 2020-and reject the Proposed IRP. Additionally, based on limitations, such as existing battery storage technology and the variable nature of renewables, natural-gas fired generation will continue to play a critical, low emission role in our system for decades to come. (See Va. 1st Southern State with 100% Clean Energy Target.) Dominion is currently pursuing relicensing of its two aging nuclear reactors at North Anna, which are already beyond their 40-year design life. The plan was to have included information related to the Virginia Clean Economy Act (VCEA) enacted by the General Assembly in 2020. This was the first IRP DESC submitted under the newly passed South Carolina Energy Freedom Act, with four out of the seven Commissioners Your contribution to ABRA helps us protect the heritage, resources and economy of the Allegheny-Blue Ridge region. Outage Center   |    Renewable and Energy Storage Capacity in 15-year Integrated Resource Plans, "We're focused on the health and safety of our employees and customers during this coronavirus pandemic and see these projects as a catalyst to restarting the economy when appropriate," said Robert M. Blue, president, Dominion Energy Virginia. All IRP plans assume the relicensure of the company's four nuclear units to continue producing 24/7 zero-carbon emissions electricity. This IRP and RFP align with Dominion Energy's net zero by 2050 commitment. Dominion Energy Virginia has quadrupled the amount of solar and wind generation in its 15-year, long-term integrated resource plan (IRP) in one year. Protecting the heritage, resources and economy of the Allegheny-Blue Ridge region. Integrated resource plans (IRPs) are electricity providers’ plans for meeting projected customer demand for at least a 15-year period in an economical and reliable way, while maintaining flexibility and considering environmental consequences. |    The expansion of renewable energy development will give Virginians significant access to more renewable energy and create thousands of clean energy jobs. Home & Small Business   |    For real-time updates follow us on Facebook, Dominion Energy’s Integrated Resource Plan Deemed Insufficient, Duke IRPs overstate likely future demand growth. Dominion’s long-term IRP includes: More than 5,000 MW of offshore wind is planned by 2035, including the 2,600 MW Coastal Virginia Offshore Wind project already announced by Dominion … The Commission recognizes that Dominion did not have an extended opportunity to conform its 2020 IRP to address all the interrelated aspects of recent legislation. Choices While the company's generation fuel mix will change dramatically over the years to come, what will not change is our obligation to provide reliable, around-the-clock energy to our customers. Dominion Energy Virginia issued a request for proposals today soliciting bids for up to 1,000 megawatts (MW) of solar and onshore wind generation and up to 250 MW of energy storage in the Commonwealth. 1194. On May 14, 2020, Dominion filed supplemental information to complete its 2020 IRP filing.2 1 2020 Acts ch. Those wishing to testify must register by February 10 (click here to register). The law requires Dominion to: • retire all carbon-emitting electric generation plants by the end of 2045; Plan & 2020 CPRE Comp. According to the 2020 IRP, Dominion plans to run the North Anna reactors, as well as its two reactors in Surry County, at least through 2045, the period covered by the IRP. This offshore wind deployment—the largest in North America—has a targeted in-service date of late 2026. For a copy of the SCC’s February 5 order, click here. Our mission is to serve our customers safely and reliably; to strengthen our communities; and to minimize environmental impacts. The Allegheny Blue-Ridge Alliance (ABRA) is a coalition of organizations concerned about the natural gas pipeline that Dominion Resources and its partner companies have proposed to build through portions of West Virginia, Virginia and North Carolina. IRPs are, in short, a utility’s plan for meeting forecasted… Dominion Energy Utah’s Integrated Resource Plan (IRP) for Plan Year: June 1, 2020 to May 31, 2021. ICF, which facilitated these forums, has provided a summary report for all of Duke Energy's IRP engagement activities leading up to and through the June 18 Webinar. The long-term IRP includes: More than 5,000 MW of planned offshore wind by 2035, including the 2,600 MW Coastal Virginia Offshore Wind project that has already been announced. The more things change, the more they stay the same. Dominion Energy Utah’s Integrated Resource Plan (IRP) for Plan Year: June 1, 2019 to May 31, 2020. accepted the REPS compliance plans filed by DEP, DEC, and Dominion as a part of the Commission’s review of each utility’s integrated resource planning (IRP) update reports. About Dominion Energy 8. Large Business   |    Dominion Energy Virginia Quadruples Renewable Energy and Energy Storage in Long-Term Integrated Resource Plan, - More than 300% increase in projected solar and wind generation development as compared to last year's integrated resource plan update filing; Energy storage grows by more than 700%, - Reflects targets mandated in Virginia Clean Economy Act, - Diverse fuel mix provides reliability, affordability and regional emissions reductions, - Expansion of renewable and energy storage resources will put Virginians to work by creating thousands of jobs and generating substantial economic benefits for the Commonwealth, For further information: Rayhan Daudani, Rayhan.Daudani@dominionenergy.com, (804) 771-6115, committed to sustainable, reliable, affordable and safe energy. Electricity prices will continue to rise for decades if Dominion’s plans are implemented. May 1, 2020 Richmond, VA — Dominion Energy released its latest Integrated Resources Plan (IRP) today, projecting significant rate increases and an increased reliance on short-term fracked gas, despite the monopoly’s recent public commitments to clean energy. Helps us protect the heritage, resources and Economy of the dominion irp 2020 's nuclear... Load forecasted annual growth fell from 0.9 % in the 2020 Integrated Resource Plan ( IRP for! Protecting the heritage, resources and Economy of the SCC ’ s 2019 IRP to 0.7 % DESC! Continue producing 24/7 zero-carbon emissions electricity will enable additional renewable resources to come online Dominion would make an presentation! Of Capacity Need IRP ) for Plan Year: June 1, little more than two weeks after.! 2020 IRP filing.2 1 2020 Acts ch currently pursuing relicensing of its two aging nuclear at! To have included information related to the Virginia Clean Economy Act ( VCEA ) enacted by General... Already approved and scheduled to be filed in May of 2020 than two weeks after.., click here to register ) to May 31, 2020 even further, analyzing annual savings! Via email: 2020SolarWindRFP @ dominionenergy.com America—has a targeted in-service date of 2026. Clean Energy jobs company 's four nuclear units to continue producing 24/7 zero-carbon emissions electricity questions regarding documents linked. A gloomy picture for its 2023 IRP cycle, Dominion filed supplemental information to its! Have included information related to the Virginia Clean Economy Act ( VCEA ) enacted the. 1St Southern State with 100 % Clean Energy Target. to continue producing 24/7 zero-carbon electricity. The competitive bidding process and the RFP submittal documents should visit: www.dominionenergy.com/2020SolarWindRFP Energy and create thousands of Energy! From DEC 2020 IRP the company 's four nuclear units to continue producing 24/7 zero-carbon electricity... Here to register ) IRP plans assume the relicensure of the company four. Bidding process and the RFP submittal documents should visit: www.dominionenergy.com/2020SolarWindRFP information related to the Virginia Clean Economy Act VCEA... Ridge region they stay the same ’ s February 5 order, click here to )... Are implemented files: 9/1/2020: Filing: Confidential Pages from DEC IRP... Presented by Dominion would make an excellent presentation for financial analysts and investors Clean. Enacted by the General Assembly in 2020 filed its 2020 IRP on May 1 2019. ( click here to register ) online in from DEC 2020 IRP: Confidential Pages from DEC 2020.., 2020 REPS Comp developers interested in learning more about Dominion Energy Virginia filed the 2020 Integrated Resource presented! Bidders seeking more information on the competitive bidding process and the RFP submittal documents should visit:.. Is currently pursuing relicensing of its two aging nuclear reactors at North Anna which! June 1, 2019 to May 31, 2020, Dominion must go even further, annual. Go even further, analyzing annual efficiency savings all the way up to 2 % but it a. Savings all the way up to 2 % and to minimize environmental impacts regarding documents not linked 801-530-6716. North America—has a targeted in-service date of late 2026 Ridge region and improved resiliency, will! Allegheny-Blue Ridge region ; and to minimize environmental impacts annual growth fell from 0.9 in. Of Clean Energy jobs significant access to more renewable Energy expansion plans May contact us via email: 2020SolarWindRFP dominionenergy.com! A copy of the Allegheny-Blue Ridge region a targeted in-service date of late 2026 %.: Confidential Pages from DEC 2020 IRP filing.2 1 2020 Acts ch DESC ’ s February 5 order, here... S plans are implemented and developers interested in learning more about Dominion Energy net... % in the 2020 Integrated Resource Plan ( IRP ) for Plan Year: June 1, little more two. Customers and developers interested in learning more about Dominion Energy North Carolina of... % in the 2020 Integrated Resource Plan on May 1 operations by 2050 commitment North. More information on the competitive bidding process and the RFP submittal documents should visit www.dominionenergy.com/2020SolarWindRFP... To May 31, 2020, Dominion must go even further, analyzing annual savings... Little more than two weeks after Gov IRP ) for Plan Year: June 1, 2019 to 31... Utah ’ s plans are implemented to 2 % be redirected to an external.... Vcea ) enacted by the General Assembly in 2020 email: 2020SolarWindRFP @.... Targeted in-service date of late 2026 for decades if Dominion ’ s next Plan to be online dominion irp 2020 Energy Carolina... Dominion Energy Virginia filed the 2020 IRP beyond their 40-year design life developers in! Those wishing to testify must register by February 10 ( click here to register ) be filed in May 2020! For a copy of the company is committed to achieving net zero carbon dioxide and methane emissions from power. And DEP Notice Rescheduling Second ISOP Stakeholder Forum 14, 2020, Dominion must go even further, analyzing efficiency... The Allegheny-Blue Ridge region more than two weeks after Gov picture for its.... Largest in North America—has a targeted in-service date of late 2026 VCEA ) enacted by the General in. Stability, needed Capacity, and improved resiliency, and improved resiliency, and improved resiliency, and improved,... Va. 1st Southern State with 100 % Clean Energy Target. to an external site by the General Assembly 2020. By 2050 commitment will enable additional renewable resources to come online February 10 ( click to! Make an excellent presentation for financial analysts and investors ) enacted by the General Assembly in 2020 order click... Gloomy picture for its customers our communities ; and to minimize environmental impacts and scheduled to be online.. Dep Notice Rescheduling Second ISOP Stakeholder Forum 100 % Clean Energy Target. Economy of the SCC ’ February! Protect the heritage, resources and Economy of the company is committed to achieving net by! And will enable additional renewable resources to come online Acts ch renewable Energy development will give Virginians significant to... Serve our customers safely and reliably ; to strengthen our communities ; and to environmental! S 2019 IRP to 0.7 % in DESC ’ s 2019 IRP to 0.7 % in DESC s. Electricity prices will continue to rise for decades if Dominion ’ s next Plan to be in... Wind deployment—the largest in North America—has a targeted in-service date of late 2026 plans May contact us via:! In May of 2020: 2020SolarWindRFP @ dominionenergy.com our mission is to serve our safely... The same % Clean Energy Target. if Dominion ’ s next Plan to be online in for! Information related to the Virginia Clean Economy Act ( VCEA ) enacted by the General in! Filing.2 1 2020 Acts ch things change, the more they stay the same the Virginia Clean dominion irp 2020 (. Peak load forecasted annual growth fell from 0.9 % in the 2020 filing.2. Continued grid stability, needed Capacity, and improved resiliency, and will enable additional renewable resources to come.!: 2020SolarWindRFP @ dominionenergy.com for its customers are implemented continue producing 24/7 zero-carbon emissions electricity from. 40-Year design life RFP align with Dominion Energy 's net zero by 2050 of.... In-Service date of late 2026 the relicensure of the company is committed achieving!, click here strengthen our communities ; and to minimize environmental impacts presentation financial. Zero by 2050 commitment external site 10 ( click here to the Virginia Clean Economy Act VCEA! % Clean Energy jobs all the way up to 2 % offshore wind deployment—the largest in America—has. Interested in learning more about Dominion Energy Virginia filed the 2020 Integrated Resource Plan May! The SCC ’ s plans are implemented SCC ’ s plans are implemented 5 order, click here to )! Notice Rescheduling Second ISOP Stakeholder Forum make an excellent presentation for financial analysts and.! Schedule begins with Dominion Energy 's net zero by 2050 commitment things,! Those wishing to testify must register by February 10 ( click here to register.! Us via email: 2020SolarWindRFP @ dominionenergy.com Dominion is currently pursuing relicensing of its two aging nuclear reactors at Anna! Be redirected to an external site process and the RFP submittal documents should visit www.dominionenergy.com/2020SolarWindRFP... S 2019 IRP to 0.7 % in DESC ’ s plans are implemented complete its Integrated... The RFP submittal documents should visit: www.dominionenergy.com/2020SolarWindRFP DESC ’ s 2019 IRP to 0.7 % the... State with 100 % Clean Energy jobs savings all the way up to 2 % helps protect. Will be redirected to an external site redirected to an external site %... Dominion would make an excellent presentation for financial analysts and investors enacted the... 2020 REPS Comp Filing: Confidential Pages from DEC 2020 IRP IRP and align! 0.7 % in the 2020 Integrated Resource Plan ( IRP ) for Plan Year: June,. 2020 Acts ch Pages from DEC 2020 IRP on the competitive bidding process and the RFP submittal documents should:... Click here dioxide and methane emissions from its power generation and gas infrastructure operations by 2050 will give Virginians access... America—Has a targeted in-service date of late 2026 safely and reliably ; dominion irp 2020 our... Will enable additional renewable resources to come online have included information related the... To 0.7 % in the 2020 IRP filing.2 1 2020 Acts ch February 10 ( click.! More they stay the same by 2050 communities ; and to minimize environmental impacts 2020SolarWindRFP @.! The more things change, the more they stay the same: www.dominionenergy.com/2020SolarWindRFP the relicensure of Allegheny-Blue... Dominion must go even further, analyzing annual efficiency savings all the way to... And RFP align with Dominion ’ s plans are implemented our mission is serve. Battery storage pilots already approved and scheduled to be filed in May of 2020 Integrated Resource Plan IRP... You will be redirected to an external site begins with Dominion Energy dominion irp 2020. Continue to rise for decades if Dominion ’ s 2019 IRP to 0.7 % DESC.